Share North Creek Road and Bridge on FacebookShare North Creek Road and Bridge on TwitterShare North Creek Road and Bridge on LinkedinEmail North Creek Road and Bridge link
Ballina Shire Council is seeking community feedback on the Concept Design, Cost Estimate and preliminary impact assessment reports for the North Creek Road and Bridge project.
This project will involve:
Reconstruction, widening and raising of North Creek Road between Forest Oak Boulevard in North Ballina and Skennars Head Road in Skennars Head
Provision of an adjacent new shared pedestrian/cycle path
Construction of a new bridge across North Creek.
The new bridge will re-establish the previous western road link between Ballina and Lennox Head that was severed in the 1970s following construction of the alternative Coast Road.
Ballina Shire Council is seeking community feedback on the Concept Design, Cost Estimate and preliminary impact assessment reports for the North Creek Road and Bridge project.
This project will involve:
Reconstruction, widening and raising of North Creek Road between Forest Oak Boulevard in North Ballina and Skennars Head Road in Skennars Head
Provision of an adjacent new shared pedestrian/cycle path
Construction of a new bridge across North Creek.
The new bridge will re-establish the previous western road link between Ballina and Lennox Head that was severed in the 1970s following construction of the alternative Coast Road.
Council’s Roads Contributions Plan and Strategic Road Network modelling identifies this project as a required link to accommodate future traffic volumes generated by urban growth areas, and to minimise existing congestion on roads between Lennox Head and Ballina.
Further road network traffic modelling is underway and due to be completed in late 2025. This review will inform future decision making in regard to this project.
Have your say
Complete the feedback form below to have your say on this major project. Please review the concept design, cost estimate and preliminary assessment reports available in the right-hand menu before completing this form.
Submissions closeWednesday 24 September 2025.
Community feedback will be collated and reported to a future council meeting where Council will consider the concept design, cost estimate, environmental impacts, landowner and community feedback, before deciding whether to proceed with and fund the next stage of this project.
Project added to Roads Contribution Plan - February 2010
North Creek Road and Bridge has finished this stage
Following public exhibition and consideration by Council, the project was included as an item in the Works Schedule of the Ballina Shire Roads Contribution Plan 2010.
Flood study - August 2021 - November 2021
North Creek Road and Bridge has finished this stage
Flood study commissioned to determine road formation height, North Creek bridge length, size and number of culverts in approaches to the bridge. These culverts are to be sized to minimise flood impacts on upstream land.
Survey of existing road - November 2021 - March 2022
North Creek Road and Bridge has finished this stage
Detailed survey of the existing road and 20m either side of the road centreline
Preparation of design/reports - December 2022 - May 2025
North Creek Road and Bridge has finished this stage
Following a public tender process, Consultants Geolink were contracted to prepare concept road and bridge design, associated cost estimates and preliminary environmental/heritage assessment.
Advice to landowners - June 2025
North Creek Road and Bridge has finished this stage
Advice to adjacent landowners on the impact of concept design on their land, followed by preliminary consultation and negotiations with affected landowners.
Public Exhibition of Concept Design - August - September 2025
North Creek Road and Bridge is currently at this stage
Public exhibition of the Concept Design, Cost Estimate and preliminary planning, environmental, geotechnical, heritage, hydrology, flooding, noise/vibration and visual assessment reports.
Report to Council - November 2025
this is an upcoming stage for North Creek Road and Bridge
Council to consider concept design and cost estimate; environmental impacts; outcomes of landowner and community consultation; and decide whether to proceed with and fund the next phase of the project.
If Council decides to proceed to next stage of project the timeline will include a formal environmental assessment and planning application/approval process followed by detailed design and preparation of tender documents for construction.